Finally Construction Resumes

2 08 2012

Yes, the moisture issues finally got worked out and work has resumed on the addition.  This was a monumental ordeal, but we worked through it without going crazy (well maybe just a little).  We are just thankful that our contractor did his best to remedy all the issues to our satisfaction and continued working to complete this project, well for the most part.

In hind sight another good decision we made before starting this project last year was to reduce the scope to just the Master Bedroom/Bath addition rather than also remodeling the kitchen and bumping out the front of the house at the same time.  Doing all of that work at the same time would have meant moving out and renting a house or apartment and  added significant cost to the project due to this lengthy construction delay.

A word of advice, is to do your remodel work in phases. Don’t think you have to do everything all at the same time.  Plus now we’re better educated on the process, which should help us make better decisions when the time comes to embark on our next home improvement project.

Here are images of work completed over the course of one month (April 2012).  It’s so good to finally see some progress again!

This slideshow requires JavaScript.

Advertisements

Actions

Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s




%d bloggers like this: