The foundation was completed this the past week.

After much digging the wood forms were installed using plenty of foundation bolts and anchors along with two double rows of rebar running through each section near the top and bottom.  (Photos 1-3)

There was an inspection on Thursday morning to ensure everything was done to code, and on Friday the concrete was flowing.  It took about 5-6 hours and 2 truck loads of concrete.  (Photos 4-6)

The concrete set over the weekend, and on Monday all the wood forms were removed and saved to reuse during framing.  (Photos 7-9)

WEEK 2 Photos – Foundation Work

Week 3 Sneak Peek – Lumber gets delivered and now the hammering literally begins!

Advertisements

Actions

Information

2 responses

27 10 2011
Bren

Love watching the progress!!!

1 11 2011
Diane

Things are definitely moving along and taking shape. Looking forward to seeing week 3!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s




%d bloggers like this: